Aberdeen Harbour Expansion

  • Client: Aberdeen Harbour Board
  • Role: Project Management and Cost Consultancy Services
  • Value: £350 million
  • Programme: January 2017 to September 2022
  • Procurement: Compliant with Utilities Regulations 2015/NEC3 Option A with Contractor Design/NEC4 Option A/NEC4 Option B/NEC4 Short Form/BIMCO Time Charter
  • Location: Aberdeen, North East Scotland

Project Description

The Problem: Aberdeen Harbour was operating at capacity and with physical constraints in the size of vessels that it could accommodate.

In 2010 Feasibility Studies commenced to review possible solutions. Ultimately the decision was to develop a new facility at Nigg Bay to the south of the existing harbour. This is not a replacement for the existing facilities but is an expansion capable of accommodating larger vessels up to 300m and deeper drafts of up to 10.5 at the deepest berth.

The new harbour will ultimately provide approximately 1400m of quays and 124,000m2 of laydown area. The Harbour is being formed by construction of two breakwaters each over 600m long. The breakwaters comprise rubble mound cores with rock armour layer and precast armour units ranging from 8m3 to 12m3 There has been approximately 2,700,000m3 of dredging required which included significant quantities of hard rock which was removed using some the world’s largest dredging plant to rip the rock. The quays are formed by a mixture of open and closed structures to satisfy wave modelling undertaken to ensure minimal downtime to operations. The Open quays will be precast structural decks constructed on 1500diameter piles and Closed Quays constructed using precast concrete caissons constructed in Spain. The use of the caisson units has enabled the harbour to expand its heavy lift capacity beyond initial expectations.

The development site was a largely undeveloped bay constrained by; a Site of Special Scientific Interest on the cliffs, presence of dolphins outwith the bay, rare plant species and the presence of the main sewage treatment plant serving Aberdeen and Aberdeenshire with two sewage outfall pipes, one of which runs below the proposed southern breakwater. Environmental Considerations have been a major influence on the planning, design and construction of the development.

Our Role / Scope

Our role in the project is to provide Project Management, Cost Consultancy and Quantity Surveying services from feasibility through to completion and handover of the new facilities. Our involvement commenced in 2012 through feasibility, options, consents, procurement and contractor selection through to Contract award at the end of 2016. The role included: programme management, budget management, consultant appointments, contractor procurement, EU funding applications and management, risk workshops, stakeholder meetings and co-ordination, cost management The appointed contractor commenced on site in 2017. In early 2020 the appointed contractor departed from the project and works substantially delayed with Covid 19 having a significant impact. Remaining works are being procured on a packaged basis and using a variety of contracts with the majority based on the NEC 4 Suite of contracts. Doig and Smith are the Project Managers and Cost Managers on all Post Contract Works.

Benefits To Client

  • All of Doig+Smith’s key team members are experienced in public procurement.
  • Significant Ports and Marine Experience.
  • Very close working relationship with the client body and a comprehensive understanding of the project requirements and constraints.
  • Flexible Team structure to suit changing project demands.

david-yorkston|douglas-fairley|stewart-cobb|transport

Client

Aberdeen Harbour Board

Role

Project Management and Cost Consultancy Services

Value

£350 million

Programme

January 2017 to September 2022

Procurement

Compliant with Utilities Regulations 2015/NEC3 Option A with Contractor Design/NEC4 Option A/NEC4 Option B/NEC4 Short Form/BIMCO Time Charter

Location

Aberdeen, North East Scotland

Looking for support on a similar project?

Contact Us

Request a Callback

Callback Request